Prevention of Future Deaths reports · 2018

David Chandler

Regulation 28 report to prevent future deaths, reference 2018-0215, written 5 Jul 2018. A coroner writes one of these when an inquest reveals a risk that could cause further deaths unless something changes.

Date of report5 Jul 2018
Reference2018-0215
DeceasedDavid Chandler
CoronerPhilip Barlow
Coroner areaNorthamptonshire
CategoryAccident at Work and Health and Safety related deaths
Sourcejudiciary.uk record · original PDF
Responses published1

The report

Text extracted from the PDF text layer. Reproduced verbatim, including the scan's own layout.

ANNEX A 

REGULATION 28:  REPORT TO PREVENT FUTURE DEATHS (1) 

REGULATION 28 REPORT TO PREVENT FUTURE DEATHS 

THIS REPORT IS BEING SENT TO: 

1.  Chief Executive, Carlsberg Supply Co Ltd 

1 

CORONER 

I am Philip Barlow, assistant coroner, for the coroner area of Northamptonshire 

2 

CORONER’S LEGAL POWERS 

I make this report under paragraph 7, Schedule 5, of the Coroners and Justice Act 2009 
and regulations 28 and 29 of the Coroners (Investigations) Regulations 2013. 

3 

INVESTIGATION and INQUEST 

On 16 November the coroner commenced an investigation into the death of David 
Chandler, age 45. The investigation concluded at the end of the inquest on 2 July 2018. 
The conclusion of the inquest was accidental death and the medical cause of death was 
inhalation of ammonia. 

4 

CIRCUMSTANCES OF THE DEATH 

On 9 November 2016 David Chandler was subcontracted to work at the Carlsberg 
Brewery in Northampton. He was employed by Speedrite NE as an engineer and was 
assisting with the removal of a dormant compressor unit. The compressor unit had not 
been used since previous work in 2014. At the time of the incident the compressor was 
isolated from the high pressure ammonia system on the discharge side using a single 
proved isolation. While Mr Chandler was assisting with the work a high pressure escape 
of gaseous ammonia occurred. Mr Chandler’s three co-workers managed to escape but 
Mr Chandler died at the scene. 

5 

CORONER’S CONCERNS 

During the course of the inquest the evidence revealed matters giving rise to concern. In 
my opinion there is a risk that future deaths will occur unless action is taken. In the 
circumstances it is my statutory duty to report to you. 

The MATTERS OF CONCERN are as follows.  –  

(1) The isolation for the 2014 work was still in place and does not appear to have been 
reviewed in the intervening period. The 2014 work was of a different nature and did not 
require physical removal of the whole compressor. There does not appear to have been 
any formal review of the appropriate isolation standard for the work in November 2016 to 
be performed safely. 

(2) Carlsberg contracted the work to Crowley Carbon who employed specialist 
refrigeration engineers. The evidence at the inquest suggested that Crowley Carbon and 
Carlsberg were each relying on the other to ensure that the compressor was safely 
isolated. 

(3) The Permit To Work (PTW) issued by Carlsberg to allow Speedrite to remove the 

1

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 compressor made reference to the 2014 PTW isolation, was completed incorrectly, and 
made no reference to hazardous substances. 

(4) Relying on the isolation from previous work on the compressor appears to have 
caused confusion as to the safe level of isolation necessary for work of a different nature 
two years later. 

6 

ACTION SHOULD BE TAKEN 

In my opinion action should be taken to prevent future deaths and I believe you and your 
organisation have the power to take such action.  

7 

YOUR RESPONSE 

You are under a duty to respond to this report within 56 days of the date of this report, 
namely by 1st September 2018. I, the coroner, may extend the period. 

Your response must contain details of action taken or proposed to be taken, setting out 
the timetable for action. Otherwise you must explain why no action is proposed. 

8 

COPIES and PUBLICATION 

I have sent a copy of my report to the Chief Coroner and to the following Interested 
Persons: 

1. 
2.  Crowley Carbon 
3.  Empire Process Engineers 
4.  Speedrite International 
5.  Speedrite NE 
6.  Health and Safety Executive 

I am also under a duty to send the Chief Coroner a copy of your response.  

The Chief Coroner may publish either or both in a complete or redacted or summary 
form. He may send a copy of this report to any person who he believes may find it useful 
or of interest. You may make representations to me, the coroner, at the time of your 
response, about the release or the publication of your response by the Chief Coroner. 

9 

5 July 2018                                            Philip Barlow 

2

Responses

1 response published against this report on judiciary.uk. A response is a body's written reply to the coroner's concerns; publication is at the discretion of the Chief Coroner's office, so an absent response does not mean nobody replied.

Response from Carlsberg UK (PDF)
Carlsberg UK

Dr Philip Barlow
HM Assistant Coroner
Coroner's Office Constabulary Block

Grisberg

UK

Carlsberg Supply Company UK Limited
Jacobsen House
140 Bridge Street

Carlsberg Supply Company UK Limited. Registered Office: 140 Bridge Street, Northampton, NN1 1PZ. Registered in England and Wales No. 8626420. VAT Reg No. GB 679 0058 12

1 Angel Square Northampton

Angel Street NNI1 1PZ

Northampton

NN1 1ED Tel +44 (0) 1604 668866

Fax +44 (0) 1604 234444
www.carlsberg.co.uk

28" August 2018

Dear Dr Barlow

inquest touching the death of David Chandler
Regulation 28 Report to Prevent Future Deaths

| am responding on behalf of Carlsberg Supply Company UK Limited ("“Car/sberg") to your Regulation 28
Report dated 5 July 2018.

| confirm that | am duly authorised to respond on behalf of Carlsberg.
Carlsberg’s response is as follows:

1) The isolation for the 2014 work was still in place and does not appear to have been reviewed in
the intervening period. The 2014 work was of a different nature and did not require physical
removal of the whole compressor. There does not appear to have been any formal review of the
appropriate isolation standard for the work in November 2016 to be performed safely.

It is agreed that the work carried out in 2014 was of a different nature to that carried out in 2016. In
2014 only the compressor unit was removed. The oil separator (to which the discharge pipework
remained connected at all times) remained in situ. The 2014 isolations on both the discharge and
suction sides of the compressor were effective throughout those works. The isolations remained in
place in readiness for a return to service of the compressor unit which had undergone refurbishment.

Those isolations remained in situ between 2014 and 2016. However, even if the isolations had failed in
some way, which they did not, ammonia would not have escaped to atmosphere because the ammonia
system was closed. In other words, even if one of the isolations failed, ammonia would have
progressed into the compressor unit only rather than to the atmosphere.

During the course of 2016 Crowley Carbon Limited (Crowley Carbon), a specialist energy efficiency
company with expertise in industrial ammonia refrigeration plant systems, conducted an energy
efficiency study and concluded that Carlsberg could make significant improvements. Carlsberg
accepted Crowley Carbon’s recommendations and appointed them as Principal Contractor and Principal
Designer (within the meaning of the Construction Design and Management Regulations 2015) for the
project.

Crowley Carbon’s recommendations, referred to above, involved the removal of the compressor unit
and the oil separator (the Works). Crowley Carbon was responsible for the planning, management and
monitoring of the Works. As Principal Designer, Crowley Carbon was also responsible for preparing and
modifying designs so as to eliminate, reduce or control foreseeable risks that may have arisen during
the Works. Crowley Carbon signed to acknowledge its acceptance of its appointment to those roles.
Therefore, Crowley Carbon had a responsibility for ensuring that the risks posed by the presence of

LNO12 (01/14)

ammonia at the site were adequately controlled and that the isolations were adequate for the purposes
of the Works.

Crowley Carbon conducted numerous site visits to enable it to plan the Works.
At all material times, Crowley Carbon:-

(a) was aware of the nature of the isolations performed in 2014 (i.e. that they were not ‘double
block and bleed’ type isolations);

{b) was aware of the likely presence of ammonia in the pipework behind those isolations;

(c) had access to the relevant Piping and Instrumentation Diagrams which identified the locations
of potential isolation points; and

(d) had access to the Permit to Work relating to the isolations in 2014.

Since the incident the isolation policy and procedures across Carlsberg have been reviewed using the
HSE guidance document entitled “The safe isolation of plant and equipment” (HSG253). The policy and
procedures now in place require any isolation to be risk assessed and implemented in accordance with
HSG253._ For each isolation, there is a defined procedure to enable trained individuals to apply an
isolation suitable to protect against the hazardous energy source. All relevant personnel have received
refresher training.

As noted above, the isolations implemented in 2014 were effective between that date and the Works
(in that they did not allow ammonia to pass). Nevertheless, Carlsberg has implemented a system to
ensure that long-term isolations are reviewed in accordance with HSG253. It has implemented a colour
co-ordinated ‘Lock-Off and Tag Out’ procedure so that long-term isolations are easily distinguished
from short-term isolations. Carlsberg has also introduced a long-term isolation register, which is
reviewed on a quarterly basis and re-validated by the Head of Engineering.

(2) Carlsberg contracted the work to Crowley Carbon who employed specialist refrigeration engineers.
The evidence at the inquest suggested that Crowley Carbon and Carlsberg were each relying on the
other to ensure that the compressor was safely isolated.

As noted above, Crowley Carbon had been appointed as both Principal Contractor and Principal
Designer. Carlsberg was relying on Crowley Carbon to ensure that the isolation was adequate having
regard to the nature of the Works.

Since the incident, and to ensure appropriate communication ahead of any future engineering work,
Carlsberg has enhanced its suite of documentation concerning the provision of pre-construction
information to relevant parties. This documentation was and is specific to each project and will identify
the hazards relevant to the works being undertaken. As part of this communication the responsibility
for isolations is clearly defined. To ensure all parties understand the role that they are assigned specific
to CDM15 Carlsberg continues to require those parties to sign a “client brief checklist”.

Carlsberg requires all potential Principal Contractors and Principal Designers to adequately demonstrate
competency in undertaking said duties and any companies not approved under the safe contractor
scheme for these critical roles are not invited to tender.

Although Crowley Carbon was aware of the nature of the isolation in place, the enhancement of the
isolation standards now in place (as detailed in the response to point 1 above) ensures that the
appropriate standard for isolation is applied irrespective of who is responsible for it.

(3) The Permit To Work (PTW) issued by Carlsberg to allow Speedrite to remove the compressor made
reference to the 2014 PTW isolation, was completed incorrectly, and made no reference to hazardous
substances.

Carlsberg has reviewed the PTW system and has concluded that it is fit for purpose. The Health and
Safety Executive attended the site on the 15 August 2017. The permit system was reviewed during that
visit and it made no recommendations for improvement.

The referencing of one permit to another is an acceptable practice within the PTW system. Post
incident practice would ensure that any previous isolations were verified against the enhanced isolation
procedure referred to in response to point 1. In these circumstances, an appropriate level of isolation
will be implemented at all times.

Since the incident, Carlsberg has reviewed the competence of individuals with responsibility for
completing PTWs. To further enhance competency, specific HSG253 training was conducted post
incident.

(4) Relying on the isolation from previous work on the compressor appears to have caused confusion
as to the safe level of isolation necessary for work of a different nature two years later.

We do not accept that there was confusion caused by the permit issued in respect of either the 2014 or
2016 works. Crowley Carbon was aware of the nature of the isolation performed in 2014. The
evidence clearly demonstrated that Crowley Carbon personnel were fully aware of the presence of
ammonia in the discharge pipework beyond the isolation on the discharge side of the compressor unit.
See the response to point 1 above. Carlsberg expected the work to be planned, managed and
monitored by Crowley Carbon so as to control those risks. See the response to point 2 above.

| believe that the above addresses all issues raised in your report.

Yours sincerely

Head of Legal

Related reports

Other reports by Philip Barlow

See all →

More reports categorised “Accident at Work and Health and Safety related deaths”

See all →

Track Accident at Work and Health and Safety related deaths

See every Prevention of Future Deaths report matching Accident at Work and Health and Safety related deaths, and how often a new one appears.

What would an alert for this have sent me? Search the full text

Free to try — the preview shows the real matches and how many arrived in the last 12 months. Your first email alert is free.

These reports are published by the Chief Coroner's office at judiciary.uk and are © Crown copyright. The text here is reproduced from the published PDF so it can be searched. If something on this page is wrong, or you are a person named in it and want it reviewed, email drcjar@gmail.com and we will act promptly.