Prevention of Future Deaths reports · 2025
Regulation 28 report to prevent future deaths, reference 2025-0374, written 24 Jul 2025. A coroner writes one of these when an inquest reveals a risk that could cause further deaths unless something changes.
| Date of report | 24 Jul 2025 |
|---|---|
| Reference | 2025-0374 |
| Deceased | James Scott |
| Coroner | Rosamund Rhodes-Kemp |
| Coroner area | Hampshire, Portsmouth and Southampton |
| Category | Road (Highways Safety) related deaths |
| Source | judiciary.uk record · original PDF |
| Responses published | 1 |
Text extracted from the PDF text layer. Reproduced verbatim, including the scan's own layout.
Regulation 28: REPORT TO PREVENT FUTURE DEATHS NOTE: This form is to be used after an inquest. REGULATION 28 REPORT TO PREVENT DEATHS THIS REPORT IS BEING SENT TO: 1 2 – Chief Executive Officer, Hampshire County Council – Chief Executive Officer, National Highways 1 CORONER I am Rosamund RHODES-KEMP, HM Area Coroner for the coroner area of Hampshire, Portsmouth and Southampton 2 CORONER’S LEGAL POWERS I make this report under paragraph 7, Schedule 5, of the Coroners and Justice Act 2009 and regulations 28 and 29 of the Coroners (Investigations) Regulations 2013. 3 INVESTIGATION and INQUEST On 09 July 2024 I commenced an investigation into the death of James Alexander SCOTT aged 25. The investigation concluded at the end of the inquest on 17 July 2025. The conclusion of the inquest was that: On the evening of 5th July 2024 James Scott, aged 25, was driving Southbound on the A33 when he lost control of the vehicle which turned sideways crossing onto the opposite carriageway colliding with a Northbound vehicle. He sustained fatal injuries and was sadly pronounced deceased at the scene. 4 CIRCUMSTANCES OF THE DEATH This report concerns a fatal road traffic collision between a Vauxhall Corsa and a Ford Ranger towing a SBS trailer upon which was a trailer, which occurred around 21:44 on Friday 5th July 2024 on the A33 near Kings Worthy, Hampshire. Mr Scott was travelling South in his Vauxhall Corsa where the vehicle has passed through an area of standing water. Consequently, the Corsa has entered a state of clockwise yaw, passing through the central reserve and into the path of the oncoming Ford Ranger which was travelling North. The Vauxhall and Ford have collided in ‘T-Bone’ formation, with Mr Scott sustaining fatal injuries and being sadly declared deceased at the scene. On examination it was observed that two of the drains to the nearside of the southbound lane were compacted with vegetation, resulting in little or no surface drainage. This is despite annual scheduled maintenance for year 2023/2024 taking place on 19th May 2023 and 15th November 2023. This included clearing gullies and catch pits either side of the A33. A Temporary “Flood” warning sign was located within the nearside grass verge, around 8 meters north of the commencement of the flooding. The ‘Temporary’ warning sign had been present for about 5 years prior to the collision. Whilst ownership of the sign is subject to debate between National Highways and Hampshire County Council, the area is known to be a flood risk and has been one for several years prior to the collision. The Forensic examiner concluded that the standing water was a contributory factor in the collision and was relevant to factors affecting Mr Scott. 5 CORONER’S CONCERNS Regulation 28 – After Inquest Document Template Updated 30/07/2021 During the course of the investigation my inquiries revealed matters giving rise to concern. In my opinion there is a risk that future deaths could occur unless action is taken. In the circumstances it is my statutory duty to report to you. The MATTERS OF CONCERN are as follows: (brief summary of matters of concern) During the course of the inquest the evidence revealed matters giving rise to concern. In my opinion there is a risk that future deaths could occur unless action is taken. In the circumstances it is my statutory duty to report to you. The MATTERS OF CONCERN are as follows. – [BRIEF SUMMARY OF MATTERS OF CONCERN] (1) The area is a known flood risk (2) Whilst the precise cause of the flooding is unknown, a more regular maintenance schedule may have prevented the buildup of vegetation within the gullies and therefore assisted in the drainage of the heavy rainfall experienced that day thus reducing the amount of surface water present on the road (3) The fact that only a Temporary Sign was in place in an area known for years to be a flood risk (4) The surface water was a contributory factor in this death 6 ACTION SHOULD BE TAKEN In my opinion action should be taken to prevent future deaths and I believe you (and/or your organisation) have the power to take such action. 7 YOUR RESPONSE You are under a duty to respond to this report within 56 days of the date of this report, namely by September 18, 2025. I, the coroner, may extend the period. Your response must contain details of action taken or proposed to be taken, setting out the timetable for action. Otherwise you must explain why no action is proposed. COPIES and PUBLICATION 8 I have sent a copy of my report to the Chief Coroner and to the following Interested Persons I have also sent it to who may find it useful or of interest. I am also under a duty to send a copy of your response to the Chief Coroner and all interested persons who in my opinion should receive it. I may also send a copy of your response to any person who I believe may find it useful or of interest. The Chief Coroner may publish either or both in a complete or redacted or summary form. He may send a copy of this report to any person who he believes may find it useful or of interest. Regulation 28 – After Inquest Document Template Updated 30/07/2021 You may make representations to me, the coroner, at the time of your response about the release or the publication of your response by the Chief Coroner. 9 Dated: 24/07/2025 Rosamund RHODES-KEMP HM Area Coroner for Hampshire, Portsmouth and Southampton Regulation 28 – After Inquest Document Template Updated 30/07/2021
1 response published against this report on judiciary.uk. A response is a body's written reply to the coroner's concerns; publication is at the discretion of the Chief Coroner's office, so an absent response does not mean nobody replied.
REGULATION 29 RESPONSE TO A REPORT TO PREVENT FUTURE DEATH
THIS RESPONSE IS BEING SENT TO:
The Area Coroner for Hampshire, Portsmouth and Southampton, Rosamund
Rhodes-Kemp, in response to a ‘Regulation 28 Report to Prevent Future Death’
following an inquest hearing into the death of James Scott.
1.
NATIONAL HIGHWAYS
I am Christine Allen, Regional Director, South East region, responding on behalf of
Nick Harris, Chief Executive of National Highways Limited, Bridge House, 1 Walnut
Tree Close, Guildford, Surrey GU1 4LZ.
2.
CORONERS MATTERS OF CONCERN
The MATTERS OF CONCERN were identified as follows:
(1) The area is a known flood risk.
(2) Whilst the precise cause of the flooding is unknown, a more regular
maintenance schedule may have prevented the build-up of vegetation within
the gullies and therefore assisted in the drainage of the heavy rainfall
experienced that day thus reducing the amount of surface water present on
the road.
(3) The fact that only a Temporary Sign was in place in an area known for years
to be a flood risk.
(4) The surface water was a contributory factor in this death.
3.
BACKGROUND
Location
The A33 Basingstoke Road southbound near Kings Worthy / Abbots Worthy
carriageway is the responsibility of Hampshire County Council (HCC). The National
Highways (NH) network then starts southbound opposite the London Road junction.
The HCC section of the highway at the staggered junction, and both roads of the
B3047, fall to the A33 with a much steeper gradient from the left junction from the
B3037 Alresford. This results in the catchment for rain / surface water to naturally run
down hill, being the A33 slip road.
Drainage
This location is a recorded flood risk site over a distance of 1523 metres in length from
the NH boundary at the London Road junction, start of A34 slip road to the end of the
A33 southbound on slip where it meets the main A34. In relation to the incident on 5
July 2024 and the coroner’s concerns, we have considered the flood events recorded
within the first 400 metres of that flood risk site.
The location of the incident is a recorded flood risk site. It is recorded as a category
B (High). The incident on 5 July 2024 has been included as a flood event in the
drainage database to inform the categorisation of this location. The grading
assessment of flood risk sites is calculated automatically by our Geotechnical Data
Management System (GDMS) monthly and is based on the number of reported flood
events at each asset location. There are only three reported incidents at this location
in the last 5 years and no further flood events have been recorded in this area since
July 2024.
Upon receipt of the coroner’s concerns, we found there to be a lack of clarity on the
ownership of the overall drainage system at this location. As a result, NH and HCC
met on site on 12 September 2025, and this has now been clarified and agreed. This
clarification is set out further on in this response.
Maintenance
As a recorded flood risk site, the maintenance frequency is increased from the
standard of every two years to twice a year for drainage assets e.g. gullies, catchpits
and channels (if applicable).
Inspection
We undertake various types of inspection of our network which serve to inform us of
the state and operability of our assets, these inspection types are principally:
o Safety Inspections – these are driven inspections of the network conducted by
our own Inspectors; at this location they take place on a weekly basis. These
inspections identify any areas of concern and defects at an early stage
enabling assessment, prioritisation and rectification. Inspectors are aware of
identified issues on their routes, including flood risk sites and focus attention
on drainage assets in those locations.
o Condition Surveys – these are technical assessments of the condition and
serviceability of the assets, for drainage assets these are conducted by
specialist 3rd party contractors on a ‘find and fix’ basis to the Design Manual
for Roads and Bridges (DMRB) standard CS 551 Drainage surveys - Part 13
and are prioritised based on the GDMS flood risk grading of an area. The
grading of this area has not currently initiated a ‘find and fix’ scheme but we
detail our plans outside of this later on in this response.
The inspection regime is carried out in accordance with our standards and severe
weather planning requirements.
Weather
To confirm, there were no weather alerts in place for the area on the day of the incident
or the days immediately preceding it.
NH and our contractors monitor weather routinely due to the impact it can have on
our business-as-usual activities. In the event of a weather alert (forecast) of severe
weather, which includes heavy rain, an impact assessment is conducted to determine
what, if any action is required to maintain the safety of road users on the network. A
severe weather event for heavy rain fall, will trigger consideration of any specific areas
of vulnerability where additional measures may be required, or additional resources
need to be stood up to affect a rapid response. This includes locations identified as
flood risk sites.
In the event of severe weather that is likely to cause disruption or impact on the
network we invoke the process detailed in our Crisis Management Manual (CMM)
which sees us escalating our operating state from ‘Normal Operations’ to ‘Regional
tactical
Alert’. This state
teleconferences which include our supply chain within the region to consider the
impact and any measures that may need to be actioned in advance of or in response
to the threat. Depending on the severity of the event this may include measures such
as additional resources, equipment or pre-emptive work prior to the arrival of the
inclement weather.
triggers multiple actions
including briefings and
4.
DETAILS OF ACTION TAKEN
Inspections
Our weekly safety inspections prior to the incident were all completed and
documented with no drainage follow up action required. Please note this was
conducted on one gully known to belong to NH at the time. Ownership of the drainage
systems in the area has now been established with HCC.
Drainage
The first drainage flood risk site visit of financial year 1 April 2024 to 31 March 2025
was ordered on 23 April 2024 with a six-month window for completion. The work was
completed on 31 August 2024. The drainage flood risk site visit prior to this was
carried out on 23 November 2023 which was flood risk site visit two for the previous
financial year.
During these works the gully lid was lifted, vegetation and detritus cleared, and the
gully jetted with any waste sucked out and removed.
M3 Junction 9 Improvement Scheme
The location of the incident has now been taken under the management of the NH
M3 Junction 9 (J9) major improvement scheme to improve congestion and traffic flow
in the wider area. The scheme is being delivered by our supply chain and overseen
by ourselves. In circumstances like this we invoke a Detailed Local Operating
Agreement (DLOA) which sets out whether the scheme or normal operations is
responsible for the maintenance and inspection activity in the area. The M3 J9 major
improvement scheme has now taken responsibility for cyclic maintenance in this area
until completion of their scheme scheduled for March 2028. Safety inspections will
remain with our NH Inspectors but with the addition of regular driven site checks by
the scheme Traffic Safety Control Officer (TSCO) who will identify and act on any
defects that arise.
Site Meetings / Maintenance Work
On 21 August 2025 the M3 J9 scheme attended the area, strimmed and jetted the
filter drains removing overburden and lifted manhole lids ensuring lines were cleared
and unburdened with sediment.
On 28 August 2025 our drainage engineers conducted a site visit to the location of
the incident. We were unsuccessful in our efforts to combine this meeting with HCC
representatives however we have since completed a collaborative visit. NH identified
the following additional work on our own network which was instructed on 2
September 2025:
1. Sweeping of kerb line on Northbound and Southbound carriageways between
London Road and A34.
2. Check side entry inlets in whole area.
3. Removal of overburden across entire area.
4. Review drainage systems from the St Marys Close Pedestrian crossing
northwards to the London Road pedestrian crossing.
5. Repair or replace eight gullies and locate outfalls in the ditch on the
southbound verge between Kings Worthy House and London Road pedestrian
crossing. [This action required HCC collaboration to clarify ownership].
6. Vegetation clearance in the ‘ditch’ line (HCC land) and clearance of
the ditch to the River Itchen. [As above this action required collaboration with
HCC to clarify ownership].
A further site visit was conducted on 12 September 2025. This was attended by
HCC’s Principal Engineer, Hampshire Police and NH Drainage Engineers plus
representatives from the M3 J9 scheme. All attendees agreed to the remedial work
instructed on 2 September 2025 above with the addition of:
7. M3 J9 scheme to arrange jetting of NH gullies to outlet.
8. A review of resurfacing extents within the M3 J9 scheme as the program
currently stops approximately 25 metres short of the current NH boundary and
an extension will avoid a double joint in a short distance.
9. M3 J9 scheme to review if drainage can be improved during the surfacing
phase of the works to remove the flat spot at the rolling crown and to gain flow
into the gullies on the southbound carriageway between London Road and
Worthy Clinic.
Full road closures of the area were implemented overnight on 15-16 September 2025
where Items 1-4 and 7 above were completed.
Signage
The temporary “Road liable to flooding” sign was on site at the time of the incident.
Our review has found the sign can be seen on site on 27 April 2023 and 21 May 2024.
At the first site visit on 28 August 2025, it was noted that the sign had been laid down
on the verge, this was reinstated by NH that day. The M3 J9 scheme has been
instructed to ensure the sign remains in place until instructed to be removed by the
NH Operations Directorate South East Drainage team upon completion of the actions
proposed and a suitable period of monitoring.
5
DETAILS OF FURTHER ACTION PROPOSED
Inspections
Weekly safety inspections will continue as planned through the NH routine program.
Drainage Work
In addition to Items 8 and 9 of the Maintenance Work above, the following further
action is to be undertaken:
1. Review of any further works identified during overnight closure on 15-16
September 2025.
2. Further works to be considered by M3 J9 scheme on the central reserve due
to the pedestrian crossing being moved out slightly to narrow the lane.
HCC to repair defective gullies at Itchen Abbas Road.
3. HCC to jet and clean drainage system from Itchen Abbas Road and Kings
Worthy House to outlet in ditch.
4. HCC to ensure ditch is clear and flowing.
5. HCC to investigate where ditch drains to and ensure functionality.
6. HCC to liaise with M3 J9 scheme team to agree traffic management
requirements and works they intend to undertake.
7. M3 J9 team to support HCC wherever possible to facilitate road space access
to complete the HCC works.
Maintenance
Regular planned maintenance will continue in accordance with the frequency
determined by NH flood risk sites. This will be delivered by the M3 J9 scheme for the
duration of their works that are due to be completed by March 2028.
Signage
No further signage action required at present due to extensive M3 J9 scheme traffic
management and signage now in place. M3 J9 scheme to ensure that “Road liable to
flooding” sign is not removed without prior consent of NH drainage engineers.
6
TIMETABLE FOR ACTION
Date
21/08/2025
Action
Central reserve filter drain remediated.
28/08/2025
15 –
16/09/2025
Re-instatement of ‘Road liable to flooding’
sign.
Complete items 1-4, 6 and 7 of the
Maintenance Work.
Item
Section 4 – Item
1
Section 4 -
Signage
Section 4
31/12/25
Repair / replacement of 3 NH owned gullies. Section 4 – Item
HCC remediation works including 5 gully
repairs / replacements.
Further works that may be required, such as
surfacing or additional drainage.
5
Section 5 – Item
2
Section 4 – Item
8-9
TBC (HCC)
TBC pending
review of M3
J9 program
7
SAFETY OF ROAD USERS
The safety of everyone on our road network matters; it is an imperative for our
business in what we set out to achieve and a core value of our organisation in how
we go about it. The action taken and planned on the A33 is designed in this light to
help to prevent future deaths at this location.
8
17 September 2025
Signed:
Christine Allen, Regional Director
South East region
See every Prevention of Future Deaths report matching Road (Highways Safety) related deaths, and how often a new one appears.
What would an alert for this have sent me? Search the full text
Free to try — the preview shows the real matches and how many arrived in the last 12 months. Your first email alert is free.
These reports are published by the Chief Coroner's office at judiciary.uk and are © Crown copyright. The text here is reproduced from the published PDF so it can be searched. If something on this page is wrong, or you are a person named in it and want it reviewed, email drcjar@gmail.com and we will act promptly.